Here is a situation we see often.
A factory owner gets three quotes for epoxy flooring. One says ₹60 per sq. ft. Another says ₹95. The third says ₹140. All three promise a “high-quality, durable floor.” The owner picks the cheapest one, because on paper they all look the same.
Six months later, the floor is peeling near the loading bay.
The problem was never the price. It was that the quotes did not say what was included. Nobody wrote down how the concrete would be prepared, how thick the epoxy would be, or what happens if something goes wrong.
This guide shows you what a good proposal contains, so you can compare quotes properly. It is useful whether you are talking to us or any other epoxy flooring contractor in Ahmedabad.
Why a detailed proposal protects you
A written proposal does three jobs:
- It makes quotes comparable. Same scope, same terms, honest comparison.
- It prevents disputes. Everyone knows what was promised.
- It reveals quality. A contractor who writes details is usually a contractor who follows them.
A one-line quote with a lump-sum price tells you almost nothing.
The 12 things every industrial epoxy flooring proposal should include
1. Project details and scope
- Your company name, site address and contact person
- The areas to be covered, with total area in sq. ft. or sq. m.
- A short description of the work
Ideally the area is broken down by zone, such as production hall, corridor, packing bay and loading area, because different zones may need different systems.
2. Existing floor condition
A good contractor records what they found during the site inspection:
- Type of existing surface (bare concrete, old coating, tiles)
- Cracks, damaged areas and uneven spots
- Moisture or dampness observations
- Oil contamination or stains
This protects you both. It shows the contractor actually looked.
3. Surface preparation method
This is the most important line in the whole document. It should say how the surface will be prepared, for example:
- Diamond grinding or shot blasting
- Removal of old coatings
- Crack and joint repair
- Dust removal and cleaning
If the proposal says only “surface cleaning,” ask questions. Poor preparation is the most common reason epoxy floors fail early.
4. Epoxy system and materials
The proposal should name the type of system, not just say “epoxy flooring.” For example:
- Self-leveling epoxy
- Epoxy mortar
- Anti-slip system
- ESD epoxy
- Chemical-resistant system
It should also mention the primer and topcoat, and ideally the material brand or specification.
5. Thickness and number of coats
This is where cheap quotes quietly cut corners. The proposal should state:
- The total system thickness (for example, in mm)
- The number of coats and layers
- Coverage per sq. ft. where relevant
Two quotes that look similar can differ hugely in how much material actually goes on the floor.
6. Colour, finish and detailing
- Colour choice
- Gloss or matt finish
- Anti-slip texture, if needed
- Treatment of edges, corners, joints and wall junctions
- Line marking, if included
7. Timeline and schedule
- Start date and completion date
- Number of working days
- Phasing plan, if the factory is running
- Curing time before light use and before heavy traffic
For help on this topic, see our guide on planning epoxy flooring installation without disrupting factory operations.
8. Site requirements from the client
A good proposal lists what the contractor needs from you:
- Clear access to the work area
- Power and water supply
- Storage space for materials
- Areas cleared of machinery or stock
- Permission for working hours
9. Exclusions
This section saves you from nasty surprises. It should say what is not included, such as:
- Major structural repairs or slab replacement
- Moisture treatment beyond a stated level
- Removal of machinery
- Work in areas not listed
If the proposal has no exclusions at all, that is not a good sign. It usually means they have not thought it through.
10. Price and payment terms
- Rate per sq. ft. and total amount
- Taxes (GST) clearly shown
- Payment schedule (advance, milestone, final)
- How extra work will be priced if needed
11. Warranty and after-service
Ask for clear written terms on:
- How long the warranty lasts
- What it covers and what it does not
- What maintenance is required to keep it valid
- Who to contact if there is a problem
Be careful of vague promises such as “lifetime guarantee” without written terms.
12. Validity, approvals and contact details
- How long the quote stays valid
- Who has authority to approve changes
- Contractor contact details and company information
A simple sample structure you can use
If you are writing your own request for quotation, here is a layout you can send to contractors so everyone responds on the same basis:
| Section | What to ask for |
|---|---|
| Area details | Zone-wise area and total sq. ft. |
| Floor condition | Contractor’s inspection notes |
| Preparation | Method and equipment |
| System | Type, brand, thickness, coats |
| Finish | Colour, gloss, anti-slip, detailing |
| Schedule | Dates, phasing, curing plan |
| Client inputs | Access, power, water, storage |
| Exclusions | What is not included |
| Price | Rate, total, GST, payment terms |
| Warranty | Duration, coverage, conditions |
How to compare factory floor coating estimates fairly
When you have two or three proposals, line them up:
| Compare | Contractor A | Contractor B | Contractor C |
|---|---|---|---|
| Site visit done before quote | |||
| Preparation method | |||
| System and brand | |||
| Thickness and coats | |||
| Timeline and curing | |||
| Exclusions listed | |||
| Warranty in writing | |||
| Total price |
Fill in the cells honestly. Often, the cheapest quote turns out to be missing half the rows.
Red flags in an epoxy flooring quotation
- A price given without seeing the site
- No mention of surface preparation
- No thickness or number of coats
- Vague wording such as “best quality materials”
- No exclusions or no warranty terms
- A price far below others with no explanation
- Pressure to pay a large advance quickly
- No written proposal at all
What does a good estimate cost, and why is it not one number?
Many people ask, “What is the rate per sq. ft. for epoxy flooring in Ahmedabad?” The honest answer is that it depends on the system, thickness, floor condition, area and preparation needed. A thin coating on clean concrete costs far less than a heavy-duty system on a damaged floor.
That is why we do not quote blindly. A site visit lets us give you a realistic figure for your actual floor. For a worked example, read our pharma epoxy flooring cost case study for a 10,000 sq. ft. plant.
How Mann Enterprise prepares proposals
At Mann Enterprise, we start with a free site visit across Ahmedabad. After that, our written proposal covers the points above: zone-wise area, floor condition, preparation method, system and thickness, timeline and curing, exclusions, price and payment terms, and warranty.
We would rather you understand exactly what you are paying for than sign something vague. If another contractor’s proposal is more detailed than ours on any point, we want to know. It usually means we should improve ours.
We are based in Swetayan Industrial Park, Kathwada, and work across Kathwada, Naroda, Vatva, Odhav, Sanand, Changodar and Bavla.
Explore our industrial epoxy flooring services in Ahmedabad. If you are still deciding who to hire, read which company installs epoxy flooring for factories in Ahmedabad.
Frequently asked questions
What should be included in an industrial epoxy flooring quotation? A good quotation includes the area, existing floor condition, surface preparation method, epoxy system and thickness, number of coats, colour and finish, timeline and curing plan, client requirements, exclusions, price and payment terms, and warranty.
How do I compare epoxy flooring quotes? Check that every quote covers the same scope: preparation method, system, thickness, coats, timeline, exclusions and warranty. A lower price often means less material or less preparation.
What is the rate for epoxy flooring in Ahmedabad? Rates vary by system, thickness, floor condition and preparation. A site inspection gives a realistic estimate for your actual floor.
Should an epoxy flooring proposal mention thickness? Yes. Thickness and number of coats strongly affect durability and cost, so they should be stated in writing.
What exclusions are normal in an epoxy flooring quote? Common exclusions include major structural repairs, extensive moisture treatment, machinery removal and areas not listed in the scope. Exclusions should always be clearly written.
Does Mann Enterprise provide a written proposal? Yes. After a free site inspection, we provide a written proposal with scope, system, thickness, timeline, price and warranty terms.
Is the site visit free? Yes. We offer free site inspections across Ahmedabad.
Get a clear, written proposal from Mann Enterprise
If you are planning epoxy flooring for your factory and want a proposal you can actually compare, call us. We will visit your site, look at your floor and give you a clear written plan and quote.
Mann Enterprise Swetayan Industrial Park, Kathwada, Ahmedabad, Gujarat 382430 Phone: +91-8155986415 Website: mannenterprise.com